Completion of the Shower.

The remaining work on the shower is only the fitting of the combined vent, Fan & Light unit, ( the ceiling is yet to be painted & the refitting of the original light but these I will leave until the remainder of the painting is done,)

Fan Vent unit over Shower reccess.

Fan Vent unit over Shower reccess.

Fan Unit

Fan Unit

The Fan / Vent unit has a wind up hatch, Blind & light unit built in.

The Fan / Vent unit has a wind up hatch, Blind & light unit built in.

The shower vent unit with the blind & Hatch open.

The shower vent unit with the blind & Hatch open.

The final stages of the Shower build.

The Shower has now been completed with the exception of the roof vent unit, using SikaFlex for the grouting was a major pain due to it tacking off quickly & causing problems when reworking at joints. I use a lot of this product & find it excellent but not for this use.

The grouting with SikaFlex is completed, this was not a fun job.

The grouting with SikaFlex is completed, this was not a fun job.

Once the grouting was completed the Shower screen was installed & all of the plumbing fittings reinstalled.

Once the grouting was completed the Shower screen was installed & all of the plumbing fittings reinstalled.

Grouting around the Freeze with the SikaFlex caused me major head aches due to the multiple lines in the freezes.

Grouting around the Freeze with the SikaFlex caused me major head aches due to the multiple lines in the freezes.

The soap dispenser & Plumbing installed.

The soap dispenser & Plumbing installed.

The shower is only waiting on the Roof vent, Fan & Light unit.

The shower is only waiting on the Roof vent, Fan & Light unit.

The Shower unit late in the build process.

The Frame work has been completed & the shower lined with 6mm Fibrous/Cement board & then water proofed. Once the cubicle was completed all of the necessary holes for the plumbing were installed, then the Tiling was started.

All of the wall panels were braced to reduce vibration before the tiles were glued in place, The tiles were set on Quality rubberized cement & the grouting has been done with SikaFlex to add strength.

Plumbing for water supply.

Plumbing for water supply.

Internal of Sheeted Unit

Internal of Sheeted Unit

Tiling of Shower has started.

Tiling of Shower has started.

1 row of tiles to go, Blue feature band & Freeze in place.

1 row of tiles to go, Blue feature band & Freeze in place.

Almost ready for grouting, sealing & Painting.

Almost ready for grouting, sealing & Painting.

Shower unit start of Installation.

The shower has been started, once the floor had been replaced after completion of the work for the Gray water tank & the rear stabilizer system the shower base & frame work was erected in place. the shower base was fitted into a hole created in the floor to allow it to be set below the existing floor level.

Shower base mounted in Frame

Shower base mounted in Frame

Steel floor sheeting to protect timber floor from road debris.

Steel floor sheeting to protect timber floor from road debris.

New Timber floor after steel plating completed.

New Timber floor after steel plating completed.

Frame work on Base of Shower.

Frame work on Base of Shower.